Welti-Furrer Pneukran & Spezialtransporte has erected a 2.3  megawatt Enercon E-70 wind turbine at an altitude of 2,465 metres, near  the border between Switzerland and Italy. The work was completed on  behalf of German company Enercon.
A Terex TC 2800-1 lattice boom  truck crane was used for the main lifts. An AC 120 Terex all terrain was  used as an auxiliary crane for setting up the boom of the TC 2800-1.
Erecting  the wind turbine at the high altitude of the Swiss Alps involved a  series of challenges. For a start the site is only accessible to  vehicles for about four months during the summer, with snow blocking the  route during the rest of the year.
Due to this short time, it  was necessary to get the massive turbine components, as well as the  crane, to the site, erect the wind turbine and disassemble the crane  again quickly. To add to the challenge, the roads for transporting the  cranes and components were narrow and winding.
"This is where the  Terex TC 2800-1's compact design and comparably small weight came in,  as it allowed us to avoid doing any damage to the roads," explained  Tobias Schöpfer, head of communications at SwissWinds Development, the  company responsible for planning and realising the project.
To  transport the turbine blades the company had to use its "Millipede" (a  specially designed multiple-axle carrier) transportation system to  ensure that they would not damage the sensitive surrounding environment.
Once  at the site, the team sent by Welti-Furrer was faced with extremely  tight space conditions, about 20 by 20 m. To ensure that they would be  working with ideal ground load conditions, the team set up the crane at  the previously inspected edge of the slope, placing 20 square metre  stabiliser pads under each outrigger.
"This enabled the crane,  with its 14 by 14 metre support base, to work with enormous lifting  capacities despite the difficult location," said Werner Häfliger, head  of the Welti-Furrer branch office in Zürich. "In fact, these lifting  capacities are significantly larger than those provided by comparable  crawler cranes (due to the greater support base), which also played a  vital role in our decision to use the Terex TC 2800-1 for this project."
With  the location secured, the help of an additional 300 tonne capacity  class crane was used to attach the front 50 m boom section.
The  lifts themselves were made more difficult by the fact that the tight  space conditions at the site prevented the team from working with the  crane's derrick boom and superlift ballast. The crane was rigged with an  assembled 96 m SH/LH boom and a counterweight of 200 tonnes.
The  crane was located 3 m above the wind turbine's foundation while  performing the work required for the project. This lifting work actually  started with the pre-assembly of the concrete towers, which required  working with a reach of 12 to 16 m. In sharp contrast, unloading the  rotor blades from the Millipede system meant using a reach of 70 m.  Finally, the actual erection process followed, this time with a working  radius of 38 m.
"The enormous range in terms of reach was yet  another important challenge that we had to deal with while carrying out  this project, but by using the Terex TC 2800-1, we were able to overcome  it without a hitch," explained crane operator Peter Häfliger.
The  project's crowning achievement was marked by the very end of the  erection process, in which the Welti-Furrer team lifted the nacelle,  together with 50 ton generator and 70 m rotor, to a hub height of 85 m.  After four straight weeks of work, the team finished the project on  schedule, despite fog, wind, snowfall and hail.
The TC 2800-1 has a capacity of 600 tonnes and can be ordered  with a crawler crane chassis (CC 2800-1) or with a truck crane chassis,  then designated TC 2800-1. The truck crane chassis, designed by Terex,  enables the basic crane to travel separately. Its star-type outriggers  allow for a maximum support base of 14 by 14 m, which provides a high  level of stability. In addition, this large support area allows the  crane to provide superior lifting capacities and enables it to perform  safe work even when used with long boom lengths. The machine can achieve  a tip height of up to 192 m, and has a maximum main boom length of 138  m.
